State Route Paving
- 1 The sidewalk being fenced off for the new road paving construction
- 2 A construction paving machine with a driver in a yellow jumpsuit in the rain
- 3 A dump truck taking away all the extra dirt at a construction site
- 4 A large yellow construction machine digging into the blocked off street
- 5 A man watching construction workers repaving a road
- 6 An excavator digging up the old rock to make room for new pavement
- 7 Construction on the street in the rain
- 8 Construction workers stripping the original concrete to make way for new
- 9 Road pavement construction with a colonial house in the background
- 10 Street pavers smoothing out the concrete
- 11 Street paving construction down the street
- 12 View of a historic downtown street torn up for new pavement
- 13 Yellow and red machines tearing up the old street for new construction
Construction Updates
| Task Name |
Duration |
Start Date |
Finish Date |
|---|---|---|---|
| Intersections SR 37-SR 158 | 7 days | Thursday, May 22, 2014 | Friday, May 30, 2014 |
| Ditch Line SR-37 | 1 day | Saturday, May 31, 2014 | Saturday, May 31, 2014 |
| Lincoln Avenue - Night work Mill and Fill - Type 2 |
5 days | Monday, June 2, 2014 | Friday, June 6, 2014 |
| Surface SR 37 T-1 Surface |
6 days | Monday, June 9, 2014 | Monday, June 16, 2014 |
| Surface SR 158 T-1 Surface |
6 days | Monday, June 16, 2014 | Monday, June 23, 2014 |
| Surface SR 22 T-1 Surface |
6 days | Monday, June 23, 2014 | Monday, June 30, 2014 |