State Route Paving

  1. 1 The sidewalk being fenced off for the new road paving construction
  2. 2 A construction paving machine with a driver in a yellow jumpsuit in the rain
  3. 3 A dump truck taking away all the extra dirt at a construction site
  4. 4 A large yellow construction machine digging into the blocked off street
  5. 5 A man watching construction workers repaving a road
  6. 6 An excavator digging up the old rock to make room for new pavement
  7. 7 Construction on the street in the rain
  8. 8 Construction workers stripping the original concrete to make way for new
  9. 9 Road pavement construction with a colonial house in the background
  10. 10 Street pavers smoothing out the concrete
  11. 11 Street paving construction down the street
  12. 12 View of a historic downtown street torn up for new pavement
  13. 13 Yellow and red machines tearing up the old street for new construction
Construction Updates
Task Name
Duration
Start Date
Finish Date
Intersections SR 37-SR 158 7 days Thursday, May 22, 2014 Friday, May 30, 2014
Ditch Line SR-37 1 day Saturday, May 31, 2014 Saturday, May 31, 2014
Lincoln Avenue - Night work
Mill and Fill - Type 2
5 days Monday, June 2, 2014 Friday, June 6, 2014
Surface SR 37
T-1 Surface
6 days Monday, June 9, 2014 Monday, June 16, 2014
Surface SR 158
T-1 Surface
6 days Monday, June 16, 2014 Monday, June 23, 2014
Surface SR 22
T-1 Surface
6 days Monday, June 23, 2014 Monday, June 30, 2014