2014 Street Paving

Construction Updates
It is important to not that all construction project schedules are dependent on the weather.
Gorsuch Area
Concrete work began on May 27, 2014.
  • 2-3 week projected time frame
  • ADA Ramp upgrades
  • Spot curb repair
Paving work began on June 9, 2014.
  • 2-3 week projected time frame
  • Begin pavement planning / placement
  • Full depth repair areas
Talmadge Area
Concrete work began June 9, 2014.
  • 2-3 week projected time frame
  • ADA Ramp upgrades
  • Spot curb repair
Paving work began June 23, 2014
  • 1 week projected time frame
  • Begin pavement planning / placement
  • Full depth repair areas

  1. 1 Sidewalk and curb ramp under construction with an orange traffic cone and yellow tape
  2. 2 A construction machine paving a road
  3. 3 A construction machine with a long crane dumping rocks and dirt into a dump truck
  4. 4 A sand truck dumping materials to pave a road
  5. 5 Pavement being roughed up by a machine to make way for new asphalt
  6. 6 Sidewalk construction with the street blocked by caution tape and orange cones

Paving Projects